Production results of Smart Energy Group for 2020

13.01.2021

Smart Energy Group announces the production results for 2020.

For the reported period the Group has

  • increased its summary gas production by 8.6% and condensate production by 4.8% y-o-y,
  • completed drilling a new well,
  • completed two workovers,
  • installed two new compressors,
  • received the grant of extension of two licences,
  • become an owner of a new licence for Svystunkivsko-Chervonolutske field through acquisition of Arkona Gas-Energy LLC.

For 2020 the total production volume by the companies of the Group increased up to 400.6 mln m3 (against 368.8 mln m3 for 2019) for natural gas and up to 34.7 Ktonnes (against 33.1 Ktonnes for 2019) for condensate.

Average daily hydrocarbons production by the companies for 2020:

Gas, Km3/day

Condensate, t/day

2020

2019

%

2020

2019

%

Enwell Energy

Representative Office of Regal Petroleum Corporation Limited

519.9

438.7

+18.5

76.4

68.9

+10.9

Prom-Energo Produkt LLC

85.4

123.8

-31.0

4.0

7.7

-48.1

PrJSC Ukrgazvydobutok

489.1

447.9

+9.2

14.4

14.0

+2.9

Smart Energy, total

1,094.5

1,010.3

+8.3

94.8

90.6

+4.6


Increase of overall production volumes by Smart Energy in 2020 is a result of wells #61 and #62 launch after workovers at Ostroverkhivske field as well as new volumes of hydrocarbons, resulted with launch of a new well (#54) at Svyrydivske field in May of 2020. Meanwhile, a decline in production rates from well #10 of Vasyshchivske field continues due to the natural depletion. Therefore, in Q1, 2020, compression equipment was installed to increase production from Vasyshchivske field. And workover is planned to commence in late Q1 of 2021 to access an alternative reservoir horizon, with the aim of boosting production from this well.

For the reported period well #25 at Svyrydivske field has been drilled to its target depth of 5,320 metres, and logging and completion operations have been performed. It is anticipated that initial testing of the well will commence by the end of January 2021. Subject to successful testing, production hook-up is planned to be completed by the end of Q1 of 2021.

Currently, planning for the drilling of well #29 at Svyrydivske field is progressing, with the well due to be spudded in Q1 of 2021. At Vasyshchivske field planning is continuing for a new well to explore the Vvdenska (VED) prospect within the Vasyshchivske licence area. At Ostroverkhivske field processing and interpretation of data of 3D-seismic studies have been completed. The results provide the ground for drilling a new well, due to be spudded in 2021 as well.

For the reported period LPG production increased from 8.4 Ktonnes for 2019 up to 9.2 Ktonnes for 2020. Upgrade of the temporary metering and separation station (TMSS) of Mekhedivsko-Golotovshchynske field is scheduled for the middle of the year. At the end of 2020 Smart Energy Group completed the design phase and received the approval by the State Labour Service of Ukraine. Preparations for upgrade works and procurement of long-lead items are underway.

Meanwhile, on March 30, 2020, Smart Energy started to prepare for construction of exploration well #4 at Svystunkivsko-Chervonolutske field the licence for which the Group received through the acquisition of Arkona Gas-Energy LLC in March last year. Nevertheless, the works have been suspended because of ongoing legal proceedings PJSC Ukrnafta initiated against the former Arkona owners and Arkona, asserting that irregular procedures were followed in the grant of the licence to Arkona in May 2017. Despite the recent ruling of the Apellate Administrative Court, as of September 29, 2020, that confirmed the regularity of licence of Arkona, the claimant filed a further appeal to the Supreme Court in Kyiv.

Last year turned out to be rather difficult and not only for the industry, but for all of us in general. Due to our numerous safety measures and high professionalism of our team, Smart Energy Group has not experienced any significant impact so far. We continued to increase production volumes and execute our projects. Nevertheless, we have pretty restrained expectations regarding a new year as lower gas prices and the global economic crisis, strengthened with pandemic COVID-19, will have their impact on gas production,” comments Sergii Glazunov, CEO of Smart Energy Group.

Reference

Smart Energy is a part of Smart-Holding and is in charge of implementing exploration projects, commercial development of the hydrocarbon deposits. It is ranked in top 5 biggest private gas producers of Ukraine, producing over 1 mln m3 of gas per day in total.

Oil & Gas business block of Smart Energy is represented by gas producing Ukrgazvydobutok (Kharkiv region) and Enwell Energy, a listed British company having assets in Poltava (the Representative Office of Regal Petroleum Corporation Limited and Arkona Gas-Energy LLC) and Kharkiv regions (Prom-Energo Product).